SJVN, operator of hydro-electric power projects, gained on Friday after the company said that, the 412 MW Rampur Hydro Electric Project located on river Satluj in Himachal Pradesh, commenced power generation with the synchronization of its first 68.67 MW unit with the northern grid.
The mechanical wet spinning of Unit-I and Unit-II of the project had been successfully achieved on Mar. 4 & 5, 2014 respectively. It is expected that all the six vertical axis Francis turbine units each of 68.67 MW will be progressively commissioned within the next three months, the company said.
Shares of the company are trading at Rs 21, up Rs 0.3, or 1.45% at the Bombay Stock Exchange (BSE) on Friday at 11:56 a.m.
The scrip has touched an intra-day high of Rs 21.25 and low of Rs 20.70. The total volume of shares traded at the BSE is 66,498.
In the earlier session, the shares rose 0.98%, or Rs 0.2, at Rs 20.70. Currently, the stock is trading down 7.49% from its 52-week high of Rs 22.70 and above 14.75% over the 52-week low of Rs 18.30.